SCOPE OF PURCHASING SERVICES
FURNITURE, FIXTURES & EQUIPMENT –
FF&E
Review of Specifications
- Coordinate with design firm(s) to verify that all specifications
and FF&E drawings are complete and accurate.
- Verify that all quantities on specifications coincide
with FF&E furniture plans.
- Obtain samples of products as required when necessary,
and track all approvals.
- Verify all quantity takeoffs with subcontractors for
those materials supplied by Owner and installed by others
(i.e.: carpeting, wallcovering, hardwired light fixtures,
etc.).
- Verify code compliance of products specified.
- Review with designer any marginally defined areas and
specifications for copyright issues on “to bid”
items, and to avoid and omissions or duplications.
Budget Preparation & Bid Process
- Prepare an itemized budget based upon quantities and specifications
provided by designer.
- Review and compare specified budget against Owners preliminary
FF&E budget.
- Create “Bid List” of manufacturers by product
with designers and Owner.
- Recommend design approved alternate sources in an attempt
to reduce costs to Owner without compromise to the design.
- Issue request for quotations to the various manufacturers.
- Create spreadsheet comparison of all bids received and
review with Owner for selection of successful bidder.
- Prepare a final budget for Owner approval.
Purchasing Process
- Prepare “Agent Only” purchase orders for
issuance to manufacturers and submit to Owner for signature.
Purchase orders to include all pertinent information such
as correct vendor name and address, complete description
of merchandise, specification reference which includes design
control number corresponding to the furniture plan and location
within the project, unit price and extension, lead time,
credit terms, delivery date, and shipping instructions.
- Advise Owner of cash flow requirements including required
deposits.
- Coordinate receipt of all required finish samples, shop
drawings, strike off’s, and samples that require designer
approval prior to fabrication and shipment of FF&E.
- Collect and assemble all flame certificates verifying
code compliance for Owner.
- Continually provide Owner with updated expediting (status)
reports of all items ordered.
- Assist in securing freight pricing and oversee movement
of all merchandise to contracted warehouse or site, as decided
by Owner.
- Continue to update budget as required and properly monitor
the overall financial parameters as determined by Owner.
- Verify and approve all invoices for their conformance
to purchase orders and design specifications, for payment
by Owner.
- All payments of invoices, be it product or freight will
be the sole responsibility of Owner. Agent accepts no responsibility
of payment of invoices.
Installation
- An Agent representative will be available for jobsite
visits on an as needed basis to be determined by Owner.
All related expenses to said visits will be billed to Owner
at cost, as incurred.
- Assist installation vendor with any related problem solving
and punch list related issues.
- Insure that receiving warehouse has all required information
necessary to the preparation of required freight claims.
|
|
|